Procurement Control Tower Procurement Control Tower
Direct materials procurement New to it? Learn by playing

Your ERP keeps the record. Control Tower works out the next move.

Stock cover, reorder points, landed cost, freight rates and delivery penalties, calculated from the reports you already export — with every formula shown and every decision kept on record.

  • Reorder points from your own lead times
  • Landed cost, not unit price
  • Liquidated damages, calculated

01 · Plan

What to buy, and when.

Every part’s cover, net of committed demand and counting what is already on the way. The verdict is on the row before anyone opens a spreadsheet.

How it decides
Order now1815% of 121
Next month1613% of 121
On track8772% of 121
Tracked121active parts
PartStockCoverVerdict
NG-MCCB-1062Moulded case breaker 4P 400A160 daysOrder now
NG-ENC-1710Wall enclosure 800×600×250633 daysOrder now
NG-MCCB-1048Moulded case breaker 3P 400A21 monthOrder now
NG-BUS-1806Copper busbar 60×10mm 3m3411 mo 12 daysOrder now

Sorted by cover. The same verdict, worked out the same way, on all 121 parts.

02 · Source

What it will really cost.

Three quotations, two currencies, two ports. Converted at the day’s rate, Aolin is cheapest. Landed — freight, duty and the charges from port to plant — it is not.

See the comparison
Quoted, converted at the day’s rateLanded: freight, duty, port to plant Ranking reversed
Halden Elektrik A.S.EUR · CFR Jeddah3,896,8353,302,402
Aolin Electric ManufacturingUSD · CFR Dammam4,095,9253,126,660
Sundar Switchgear Pvt LtdUSD · CFR Jeddah4,100,4993,361,065
Aolin, as quoted175,742SAR cheaper than Halden
Aolin, landed199,090SAR dearer than Halden

Totals for four copper busbar lines, 7,200 pieces, in SAR.

03 · Commit

Turn the award into a dated promise.

An award is not a delivery. A schedule reference carries the committed dispatch date and quantity, and every later question is asked against it — even after the date moves.

See the commitment
Active entries51
Overdue arrivals7
Arriving ≤ 30 days2117,216 units
Docs to chase50
HALDEN/SR-9001PO 4512088 · 2,800 pcs NG-BUS-1795 copper busbar28 days late
4 MayAward finalised
30 JunCommitted dispatch
RevisedSupplier delay — basis stays 30 Jun
28 JulDispatched

The date moves to keep the plan honest. A supplier's delay still counts from the original promise.

04 · Expedite

Chase what is late, not what is loud.

Every open order carries its own thread: what the supplier said, who logged it, and when to ask again. Orders nobody has ever chased are counted on their own.

How to chase a supplier
Overdue0
Due today0
Never chased4
Upcoming48
PO 454514 · NG-PLC-1288 · Alcazar Cooling Systems

“Supplier confirms production complete, awaiting inspection release.”

9 Aug
PO 454500 · NG-MCB-1005 · Aolin Electric

“Partial shipment agreed: balance to follow on the next vessel.”

8 Aug
PO 454515 · NG-IOM-1301 · Cotronic Endustriyel

No follow-up yet

Needs first

05 · Claim

The clause you already have, calculated.

0.75% of the value per week after seven days’ grace, capped at 3%. Entered once, it works itself out per part and per schedule reference — and prints as a statement.

Run it yourself
Delayed goods · 2,800 × 527.941,478,232 SAR
Days late, less 7 days’ grace28 − 7 = 21
Rate · 0.75% × 21 ÷ 72.25%
Cap3% · not reached
Damages calculated · Halden Elektrik 33,260.22 SAR
0%2.25% of a 3% cap3%

Statement ready to send

06 · Report

The same work, added up.

Nobody rekeys anything to produce it. Spend, landed against quoted, freight per kilometre and the sales pipeline, read straight from the records the week already made.

Open the analytics
Parts planned121
Suppliers25
On order, SAR3,267,416
Jan 2025Spend by monthAug 2026: 4,809,253

Twenty months of purchase spend, in SAR — the same figures as the chart on the Analytics page.

It runs on six reports your ERP already exports. Nothing is written back.

  • Stock on hand
  • Open purchase orders
  • Open sales orders
  • Goods receipts history
  • Consumption history
  • Bills of material
  • Your column names, not ours

New to procurement?

Try the job for sixty days. It takes one minute.

Every business that sells things has to decide when to buy more. Order late and the shelf goes empty; order early and money sits in stock. A truck takes six days, and customers will not wait.

Play it, then watch a reorder point play the very same days. That one sum is the first thing this software does, for every part, every week.

Keep the shelf stocked for sixty days

Day 0 of 60

This is a game when JavaScript is on. The idea it plays out: a truck of 100 takes six days to arrive and customers take about ten a day, so you have to order when about sixty are left, plus whatever you keep back for a busy week. Order later and the shelf runs empty before the truck comes.

60 on the shelf
0days the shelf was empty
0trucks on the road, 6 days each
~10sold on a normal day

You are the buyer. Press start, and order a truck whenever you think it is time.

The problem

The data already exists. The decision doesn’t.

Every number is already there

Stock on hand, open purchase orders, confirmed sales demand, goods receipts, consumption history. Everything needed to decide what to buy is in a system somewhere.

It arrives as four spreadsheets

Stock in one tab, open orders in another, sales orders in a third, lead-time assumptions in somebody’s head. The merge is manual, error-prone, and redone from scratch every week.

And the reasoning disappears

The order gets raised. Three months later nobody can reconstruct why that quantity, from that supplier, on that date — because the reasoning only ever existed in a meeting.

Stock on hand
Open purchase orders
Open sales orders
Lead times
One row, decided
NG-BUS-1806 · Copper busbar 60×10mm 3m
341 in stock · nothing on order · 1 month 12 days of cover
Order now

A worked example

The cheapest quotation was the most expensive purchase.

Three suppliers quote the same four copper busbar lines, in two currencies, into two ports. Scroll through what happens next.

01

Three quotations, three sets of terms

Halden Elektrik quotes euros into Jeddah. Aolin Electric quotes dollars into Dammam. Sundar Switchgear quotes dollars into Jeddah. Same four lines, 7,200 pieces — and nothing on the page is comparable yet.

02

Converted, Aolin is cheapest

At the day’s rates, Aolin’s quotation totals 3,126,660 SAR against Halden’s 3,302,402 — cheaper by 175,742 SAR. Most comparisons stop here.

03

Landed, the ranking reverses

Add freight, duty and the charges from port to plant. Halden lands at 3,896,835 SAR and Aolin at 4,095,925 — dearer by 199,090 SAR. Same quotations, opposite answer.

04

A 70/30 award, with its reasons kept

Halden takes 2,800 pieces on “lowest landed cost after negotiation”; Aolin takes 1,200 “to protect continuity of supply”. What that second source costs — 59,727 SAR — gets a tile of its own rather than being left to be discovered.

Follow it end to end

NG/RFQ/2026/001 · four busbar lines Ranking reversed
Quotations receivedEUR · USD · USD
Cheapest as quoted · Aolin−175,742 SAR
Cheapest landed · Halden−199,090 SAR
Awarded value3,956,562 SAR
Halden Elektrik A.S.EUR · CFR Jeddah3,896,8353,302,402
Aolin Electric ManufacturingUSD · CFR Dammam4,095,9253,126,660
Sundar Switchgear Pvt LtdUSD · CFR Jeddah4,100,4993,361,065
First line, awarded
Halden 70% · 2,800 pcsAolin 30%

Totals in SAR. Bars on a common scale from zero.

The weekly loop

An hour on a Monday, not a project.

It starts on an ordinary week, with the reports your team already exports. No connector, no middleware, no IT project.

01

Refresh

Drop in the exports you already run. A mapping engine reads your column names, not ours, and records every upload in a ledger: which file, when, and who.

02

See

Every item in one table: stock available, open sales demand, open purchase orders, arrivals month by month, and months of cover.

03

Decide

Order now, order next month, or on track — computed from your own lead times, safety stock and service levels, with the formula shown.

04

Record

Run the review inside the app. Actions, owners and outcomes become an audit trail instead of evaporating when the meeting ends.

The six jobs it does, in full

Coverage

From forecast to freight, in one place.

Every screen grouped into the five questions a procurement team actually has to answer — on one login and one set of numbers.

Plan

What will we need, and when do we run out?

  • Cockpit
  • Calendar
  • Forecast Lab
  • Formulas
NG-MCCB-10620 days
NG-ENC-17103 days
NG-MCCB-10481 month
NG-BUS-18061 mo 12 days
NG-OLR-11611 mo 25 days

Months of cover, on a two-month scale. NG-OLR-1161 has 204 in stock against 112 a month on a two-month lead time.

On your phone

A separate phone interface, not the desktop squeezed onto a small screen.

Schedules on a phone: a bar splitting every scheduled delivery into late, overdue, due, in transit and planned, then the next eight weeks as one lane per supplier, with late deliveries drawn as squares, and the late ones listed first with how many days late each is.

Source

Who supplies it, at what landed cost, approved by whom?

  • Sourcing
  • Workflow
  • Follow-ups
Halden · EUR4.779
Aolin · USD4.913
Sundar · USD4.575

Landed riyals per unit of each supplier’s currency.

Move

Where is it, what did it cost to land, and who was late?

  • Logistics
  • Schedules
Curtainside6.09
Flatbed5.76
Box truck4.47
Van3.46

SAR per kilometre, from the company’s own freight invoices.

Sell

What did we promise customers, and at what price?

  • Sales
  • Quotations
925,168SAR won · 7 quotations
484,331SAR out with customers
64%win rate · 7 won, 4 lost

Govern

Who decided what, on what evidence?

  • Meetings
  • Decisions
  • Analytics
  • Refresh
  • Team
  • 69 decisions recorded across 50 items
  • Not one of them without a reason
  • Every upload recorded: which file, when, who
  • Approvals enforced by the database

Every screen, area by area

Two questions you will have

Your ERP keeps its job. Your data keeps to itself.

Your ERPSix standard exports
Procurement Control TowerYour company’s data, and only yours

It never writes to your ERP

It reads six reports your ERP already exports, and writes nothing back. No connector, no middleware, no ERP project. If it disappeared tomorrow your ERP would not notice.

What it reads, and what it never writes →

100%

of tables locked to a single company

Enforced by the database and audited on every deploy, not by the application remembering to ask.

900+

automated tests before anything ships

Every screen, desktop and phone, plus the arithmetic behind them. Backups run daily to separate infrastructure.

Security and data isolation →

Nineteen steps, one requirement, every number checkable.

The clearest way to judge this is to follow a single purchase from the warning that raised it to the claim that closed it — on real screens, with arithmetic that survives being added up.